Bond Project Update: June 2023
Summer is officially upon us! Many of our students and educators are taking a well deserved break, but our construction crews are still moving forward with a host of exciting bond-funded projects. Thank you to our voters for approving our School Construction Bond in 2019!
New Naches Trail Elementary
Construction on the New Naches Trail Elementary School is ongoing. (see photo above) The 77,000-square foot school will soon house 41 general classrooms! This new, larger school will allow us to work towards accommodating projected growth in the area.
Evergreen Elementary Expansion
Once the New Naches Trail is complete, the old Naches Trail Elementary will become home to the Evergreen Elementary staff and students while the renovation and expansion of their school takes place. The Evergreen Elementary project will expand and modernize the current building, which was originally built in 1979. This month, the final version of the Educational Specifications was approved by the Board.
Elementary #19
Construction crews have broken ground on our 19th Elementary School! The 68,000-square-foot building will house about 500 students and will be located in the Lipoma Firs Community.
Graham-Kapowsin High School Expansion
Construction is wrapping up on the Graham-Kapowsin High School expansion project. The 33,000-square-foot expansion is adding a new classroom wing, an auxiliary gym and weight room, along with a larger commons area and administrative spaces. GKHS will also soon be home to a new School-Based Health Clinic, the construction of which is being funded through a congressional award.
New Bethel High School
Construction on the New Bethel High School project is anticipated to begin in 2024, subject to permitting. Once started, the construction timeline is 27 months. There will be an Open House for this project in September, 2023. More information will be sent to families and community members closer to the event.