Bond Project Update: September 2024
Thank you, voters!
Expedition Elementary is open!
Thank you to our amazing construction team for having Expedition Elementary ready for the first day of school! Our newest bond-funded school is 66,000-square-feet and located in the Lipoma Firs Community. It’s now home to about 500 students in 27 general classrooms and various shared spaces. Thank you, voters!
Cedarcrest Middle School
Thanks to increased state funding, better-than-expected estimates, and responsible fiscal management, we are now able to proceed with building a new Cedarcrest Middle School instead of modernizing the existing one! More details to come on this project, but kudos to our Construction Team for their hard work ensuring our students and staff will have the best possible learning environment!
Evergreen Elementary Expansion
Camp Evergreen is open for business! This year, Evergreen Elementary staff and students are “glamping” at the old Naches Trail building, while Evergreen gets its extreme home makeover thanks to our voters!
The much needed expansion of Evergreen Elementary will add 10,000 square feet to the school, which will include eight additional classrooms and a new commons.
New Bethel High School
Our construction crews have been busy since we broke ground on the new Bethel High School in March! The timeline for the project is 27 months from the start of construction.